The TxDOT highway letting is scheduled for November 1st & 2nd. The total tonnage of asphalt pavements being let is 434,795.
| # | COUNTY | HWY |
TYPE | TONS |
| 1 | BANDARA |
PR 37 |
GRADING, BASE, SURF, PAV MRK, SIGNS |
1,984 |
| 2 | BOWIE |
US 59 |
PLANING,ACP,CPCD & PAV MRKS |
3,985 |
| 3 | BRAZOS |
SH 6 |
HMA MILL AND INLAY |
800 |
| 4 |
CARSON |
IH 40 |
REHAB EXISTING ROADWAY |
45,457 |
| 5 |
COLLIN |
FM 455 | SHLD WDN,BS REP,SEAL,LVL-UP |
18,135 |
| 6 |
DENTON |
US 380 |
STRUCTURES, BASE, PAVEMENT |
17,603 |
| 7 | DENTON | US 377 | BASE REP, OV |
46,851 |
| 8 | FORT BEND |
FM 2977 |
INSTALL LEFT TURN LANES |
4,835 |
| 9 | FORD BEND |
SH 99 |
GUARDRAIL REPAIR |
30 |
| 10 |
FORD BEND |
MR 668 |
CONTRUCT NEW PARKING LOTS |
2,638 |
| 11 |
GALVESTON |
FM 2004 |
INSTALL TURN LANES |
562 |
| 12 |
GRIMES |
SH 90 |
REHABILITATE EXISTING ROAD |
21,548 |
| 13 | GRIMES |
SH 30 |
ADDITION OF A LEFT TURN LANE AT CR 175 |
2,735 |
| 14 | HARRIS |
US 45 |
GR, WIDEN STRS & RECONSTR PV |
23,480 |
| 15 |
HARRIS |
US 59 |
RECONSTRUCT FRONTAGE ROAD |
23,756 |
| 16 | KARNES |
US 181 |
INTERSECTION IMPROVEMENTS |
10,926 |
| 17 | KERR |
FM 394 |
REHAB ROAD |
1,101 |
| 18 | LEE |
SH 21 |
ADD SHLDRS., PAV REPAIR, SEAL COAT |
33,385 |
| 19 |
LIBERTY |
FM 1960 |
ACP, STRIPE |
17,125 |
| 20 | LIBERTY |
FM 686 |
BS, ACP, OCST, STRIPE |
7,568 |
| 21 |
MONTAGUE |
FM 677 |
REHABILITATION OF EXISTING ROADWAY |
23,261 |
| 22 |
MONTGOMERY |
CR |
REPLACE BRIDGE AND APPROACHES |
743 |
| 23 |
NACOGDOCHES |
VA |
ADDITION OF TWO LEFT TURN LANES |
1,034 |
| 24 |
RANDALL |
CS |
REHAB EXISTING ROADWAY |
4,726 |
| 25 |
SABINE |
SH 87 |
PROVIDE ADDL PAV SURF WID & TURN LN |
7,985 |
| 26 |
TARRANT |
SH 199 |
GRADING, DRAINAGE AND STRUCTURE |
4,468 |
| 27 |
TARRANT |
US 287 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR |
2,450 |
| 28 |
WALLER |
FM 3346 |
ACP OVERLAY |
5,447 |
| 29 |
WHEELER |
FM 592 |
WIDENING OF NON-FREEWAY FACILITY |
41,118 |
| 30 |
ZAPATA |
US 83 |
REHAB & WIDEN PAVEMENT (SUPER 2) |
59,059 |
| TOTAL | 434,795 |