Facebook Twitter Twitter    Archive | www.aapa-ports.org February 19, 2013
   

Virginia: Craney Island Containment Dikes Break Surface of Elizabeth River

Print Print this Article | Send to Colleague

The two southern-most dikes needed for the development of the Virginia Port Authority’s Craney Island Marine Terminal began poking through the Elizabeth River’s low-tide line in early February. 

In 2010 dredge contractors began pumping tens-of-thousands of cubic yards of sand taken from the Atlantic Channel maintenance dredging project and “repurposing” the material in construction of the dikes. The repurposed material is being spread in two orderly rows – perpendicular to the Craney Island shoreline – by a “spill barge,” a vessel specially designed for controlling the placement of the sand. 

Dike construction underway at the site of Virginia’s future Craney Island Marine Terminal.
Photo/Virginia Port Authority

When completed in mid-to-late March, the dikes will be 2,000 feet long, 500 feet wide and 10 feet tall. The next phase of work will be to connect those dikes at their ends with a long dike that runs parallel to the shoreline. From above, the project will look like a large rectangle (“cell”) with the shoreline as one of its long sides. A second cell will be developed and filled at a later date. 

Once the dike construction is complete, the focus of work will shift to filling the rectangle with more repurposed dredge material that will be taken from regional dredging projects; it is anticipated that filling the cells will take between six and eight years. When the dike-and-fill phase is done, the work will result in the creation of a 600-acre foundation for Craney Island Marine Terminal. 

The first phase of this project is to build the land on which the marine terminal will sit,” Rodney W. Oliver, PPM®, the VPA’s interim executive director. “It is, by far, the most complicated and costly part of the project. Once that 600-acre plot is in place, it will be there for us to develop as we need, as demand dictates. Comparatively, building a marine terminal will not be nearly as complicated.” 

The first marine terminal at Craney Island could open within 12 to 15 years, depending on need. 
 

Share Share on Facebook Share on Twitter Share on LinkedIn