Fox Island Wind receives overwhelming customer support

Print Print this article | Send to Colleague

Installing wind turbines on an island off the Maine coast has its own special problems, according to Charles (Chip) Farrington, general manager of the Fox Islands Electric Cooperative, Inc.

The Coop serves two small islands accessible by a 1 hour and 20 minute ferry ride from Rockland, Maine and during the winter serves less than 2,000 customers. The islands' populations more than triple during the summer months. Before wind power came to the island, the population depended on underwater cables from the mainland to bring electricity. This often caused reliability problems and resulted in very high electric rates.
 
The wind project began in 2001 when the cooperative applied for and received a grant for a three-year wind-resource study conducted by the University of Massachusetts Renewable Energy Research Laboratory. When the results indicated that wind power was a viable option for the utility, Farrington began working with General Electric specifications to do a financial analysis which then led to a feasibility study.

Click here to get details of the projects financing and planning.

Dr. George Baker, a seasonal resident of Frenchboro Island and a Harvard Business School professor, was engaged to do a preliminary economic analysis and create a financial plan. The Coop then entered the feasibility stage, which included an engineering study and an economic strategy. In July 2008 the ratepayers on both Vinalhaven and North Haven voted overwhelmingly 382 to 5 in favor of the project.

Getting the large turbines and blades over to the island on barges was no easy task and getting them from the shore to the site via narrow, winding roads proved very difficult - however, not impossible, as construction commenced on June 8, 2009. At the same time it was discovered that upgrades to the islands' main substation were needed and a race to the finish line ensued. The substation was ready to go two days before the completion of the three towers and a grid tie-in took place in October. General Electric begin the commissioning process for the turbines in November and Fox Islands Wind generated its first kilowatts during its testing. GE trained utility Lineworkers Loren Bunker and Joe Bickford in the operation and maintenance of the units.

Sixty percent of the wind power stays on the island and 40 percent is sent via cable to ISO New England. The electric rates on the island have been reduced by 15 to 20 percent and residents are highly supportive of the Fox Island Wind.

"The hardest part was getting started," said Farrington. "The feasibility of the project had many aspects that needed to be explored but it was all challenging and worthwhile."